200062 - Establishment of Small Industrial Estate at Bajaur (AIP) (PC-II Approved)
Approved cost of the Project : 401.34
Project Start Date : 01/07/2021
Project End Date : 30/06/2023
Project Area : AIP
Updated progress:
- Progressive Exp: 0
- CFY Allocation: 150
- CFY Release : 150
- CFY Expenditure: 0
- PC-I for land acquisition approved on 15-11-21 at the cost of PKR 401.341 million for purchase of 370 kanal land in Sheikh kaly, Tehsil Khar.
- Partial payment in land acquisitio cases is not possible. Therefore, arrangements may kindly be made for release of full approved cost.