Rashakai Special Economic Zone Project (Electricity - 210MW & Gas) (KP)

Rashakai Special Economic Zone Project (Electricity - 210MW & Gas)

Approved cost of the Project : 3,028.76

Project Start Date : 23/05/2025

Project End Date : 23/05/2025

Project Area : KP

  • Exp till 30th June 2021: 2,846.184
  • Total Physical/ Financial Progress : 100 %

 

  • 10 MW Electricity to RSEZ is 100% completed.
  • 150 MW Electricity to RSEZ is 90% completed.
  • 50 MW Electricity to RSEZ is 20% completed.
  • Gas to RSEZ is 100% completed.
  • Inaugurated by the PM Imran Khan dated 28/5/2021.


Issues:


  • Crossing of Transmission Line through Motorway is pending.
  • NOC of NHA for ROW is pending